ExamArmor Reference
The Complete AWS Cloud Computing Glossary
Master the essential vocabulary and exam context for the AWS Solutions Architect Associate, Cloud Practitioner, Developer Associate, and DevOps Engineer Professional certifications.
A
Acceptance Criteria
ScopeAcceptance criteria are the specific, testable conditions a deliverable must meet before the customer accepts...
Acceptance-Test-Driven Development (ATDD)
EngineeringATDD writes the acceptance tests collaboratively — customer, developer, tester together — before development b...
Accountability vs Responsibility
TeamAccountability is answering for the outcome — it belongs to exactly one person and cannot be shared or delegat...
Activity
ScheduleAn activity is a distinct, scheduled piece of work with a duration, resources, and usually dependencies — the...
Actual Cost (AC)
EVM & CostActual Cost is the simplest of the three EVM numbers: the total money actually spent to accomplish the work co...
Adaptive Life Cycle (Agile)
FundamentalsAn adaptive (agile, change-driven) life cycle fixes time and cost into short iterations and lets scope flex: b...
Affinity Diagram
PlanningAn affinity diagram organizes a large messy set of ideas into natural clusters: everyone writes items on cards...
Agile Coach
AgileAn agile coach develops agile capability beyond a single team — coaching teams, leaders, and the organization...
Agile Manifesto
AgileThe 2001 Agile Manifesto states four value pairs: individuals and interactions over processes and tools, worki...
Agile Mindset
AgileThe agile mindset is the belief system beneath the practices: value flows from learning fast, people closest t...
AI Ethics & Governance in Projects
EmergingWhen projects use or deliver AI, governance questions become project management questions: data privacy (what...
AI in Project Management
EmergingAI in project management spans machine assistance across the life cycle: schedule risk prediction from histori...
AI-Augmented Project Management (PMP 2026)
EmergingThe 2026 PMP expects working literacy in AI as a PM tool: predictive analytics (schedule/cost risk forecasts f...
Alternatives Analysis
PlanningAlternatives analysis is the structured comparison of different ways to achieve an objective — build vs buy vs...
Analogous Estimating
CostAnalogous (top-down) estimating prices new work by comparing it to similar past work, adjusted for differences...
Artifact
FundamentalsAn artifact is any document, template, output, or deliverable produced while managing a project — charters, re...
Assumption Log
PlanningThe assumption log records what you're treating as true without proof (assumptions) and what you must work wit...
B
Backlog Refinement (Grooming)
AgileBacklog refinement is the ongoing activity of keeping the backlog ready: splitting epics into stories, clarify...
Behavior-Driven Development (BDD)
EngineeringBDD extends TDD by writing examples of system behavior in business-readable language — Given/When/Then — agree...
Benchmarking
QualityBenchmarking compares your practices, processes, or metrics against comparable projects or organizations — int...
Benefits Delivery Phase
Benefits ManagementThe benefits delivery phase is the period in a program's life cycle when component projects and program activi...
Benefits Identification
Benefits ManagementBenefits identification is the first phase of program benefits management — the process of figuring out exactl...
Benefits Management Plan
ProgramThe benefits management plan defines each intended benefit, how and when it will be measured, who owns it, and...
Benefits Realization
ProgramBenefits realization is the discipline of ensuring a project or program actually produces the business value t...
Benefits Register
ProgramThe benefits register lists every planned benefit with its measure, baseline, target, timing, owner, and curre...
Benefits Sustainment Plan
Benefits ManagementA benefits sustainment plan is the document that defines how the benefits delivered by a program will be maint...
Benefits Transition & Sustainment
ProgramBenefits transition hands delivered capabilities to the operational owners who will run them; sustainment ensu...
Bidder Conference
ProcurementA bidder conference is the meeting where all prospective sellers hear the buyer's requirements and ask questio...
Bottom-Up Estimating
CostBottom-up estimating prices every work package individually — ideally with the people who'll do the work — the...
Budget at Completion (BAC)
EVM & CostBudget at Completion is the total authorized budget for the entire project — the finish-line number all other...
Burndown Chart
AgileA burndown chart plots remaining work (story points, hours, or tasks) against time, falling toward zero as a s...
Burnup Chart
AgileA burnup chart plots completed work rising toward a total-scope line over time. Unlike the burndown, it shows...
Business Analysis
BusinessBusiness analysis is the discipline of identifying business needs and defining solutions that deliver value —...
Business Case
ProgramThe business case is the document that justifies the investment: the problem or opportunity, the options consi...
Business Need & Business Objective
BusinessThe business need is the problem or opportunity that justifies doing anything at all — falling retention, a ne...
Business Value
BusinessBusiness value is the net benefit an initiative creates — tangible (revenue, cost savings, market share) and i...
C
Cadence
AgileCadence is the rhythm work runs on — the fixed heartbeat of sprints, releases, planning, and reviews. A steady...
Capability
ProgramA capability is the organizational capacity to do something it couldn't before — run same-day fulfillment, und...
Change Control Board (CCB)
ScopeThe Change Control Board is the group with the authority to approve, defer, or reject change requests — typica...
Change Control System
IntegrationThe change control system is the machinery that executes the change management plan: the forms, the tracking t...
Change Management Plan
IntegrationThe change management plan defines how changes will be handled before any change exists: who may submit reques...
Change Request
IntegrationA change request is the formal proposal to modify any project document, deliverable, or baseline. Four flavors...
Claims Administration
ProcurementClaims administration is the process of documenting, monitoring, and resolving contested changes — situations...
Code of Accounts
CostThe code of accounts is the numbering system that uniquely identifies every WBS element (1.2.3 = project 1, de...
Colocation (War Room)
TeamColocation places the team physically together — same room or floor — to maximize the highest-bandwidth commun...
Communication Management Plan
CommunicationThe communication management plan defines who needs what information, when, in what format, and from whom — pl...
Complexity
FundamentalsComplexity is the project characteristic arising from many interacting elements — human behavior, system inter...
Component Authorization
GovernanceComponent authorization is the formal process by which a program manager officially approves a component proje...
Component Projects
ProgramComponents are the projects, subsidiary programs, and other work inside a program. Each has its own manager, p...
Conflict Resolution Techniques
LeadershipPMI recognizes five approaches: collaborate/problem-solve (dig into the real issue, win-win — the default righ...
Constraint
FundamentalsA constraint is a limiting factor the project must work within — a fixed deadline, a capped budget, a regulati...
Contingency Plan
RiskA contingency plan is the pre-built response that executes if an identified risk fires — designed calmly in ad...
Contingency Reserve
RiskContingency reserve is time or money set aside for identified risks — the "known unknowns" already sitting in...
Continuous Delivery
EngineeringContinuous delivery keeps the product permanently releasable: every change that passes the automated pipeline...
Continuous Integration (CI)
EngineeringContinuous integration means every developer merges small changes into the shared mainline at least daily, and...
Control Account
CostA control account is a management point on the WBS where scope, budget, actual cost, and schedule are integrat...
Control Chart
QualityA control chart plots process measurements over time against a center line and statistically derived upper/low...
Corrective & Preventive Action
MonitoringCorrective action realigns performance with the plan after a deviation has occurred; preventive action interve...
Cost Baseline
CostThe cost baseline is the approved, time-phased budget for the project work — not just a total, but when the mo...
Cost of Quality (CoQ)
QualityCost of quality is everything you spend because quality matters — split into the cost of conformance (preventi...
Cost Performance Index (CPI)
EVM & CostCPI measures cost efficiency: how much value the project earns for every dollar spent. A CPI of 1.0 means you'...
Cost Variance (CV)
EVM & CostCost Variance is the dollar gap between the value of the work performed and what it cost: negative means over...
Cost-Benefit Analysis
BusinessCost-benefit analysis compares what an option costs against what it returns, in money, so alternatives can be...
Cost-Reimbursable Contract
ProcurementIn a cost-reimbursable (cost-plus) contract, the buyer pays the seller's legitimate actual costs plus a fee —...
Crashing
ScheduleCrashing is schedule compression by adding resources to critical path activities — more people, overtime, prem...
Critical Chain Method (CCM)
ScheduleCritical chain scheduling accounts for resource limits, not just task logic, and attacks a human truth: people...
Critical Path
ScheduleThe critical path is the longest sequence of dependent activities through a project — and therefore the shorte...
Critical Path Method (CPM)
ScheduleThe Critical Path Method is the analytical technique behind the critical path: a forward pass through the netw...
Cross-Functional Team
AgileA cross-functional team contains, inside itself, every skill needed to turn an idea into a finished increment...
Crystal Methods
AgileCrystal (Alistair Cockburn) is a family of methods tuned by team size and criticality — Crystal Clear for a co...
Cumulative Flow Diagram (CFD)
AgileA cumulative flow diagram stacks the count of work items in each state (to do, in progress, done) over time as...
Customer
StakeholderThe customer is whoever will approve and manage the project's product, service, or result — and often the one...
Cycle Time
AgileCycle time measures how long a work item takes from when work starts on it to when it's done. Its sibling, lea...
D
Daily Standup (Daily Scrum)
AgileThe daily standup is a 15-minute team synchronization: inspect progress toward the sprint goal, surface impedi...
Dashboard
MonitoringA dashboard presents project health at a glance — KPIs, trends, RAG statuses, burn charts — tailored to its au...
Data Date (Status Date)
ScheduleThe data date is the as-of point for all project status: everything to its left is actuals, everything to its...
Decision Tree Analysis
RiskA decision tree maps a choice and its uncertain outcomes as branches, attaches probabilities and payoffs to ea...
Decomposition
ScopeDecomposition is the technique of breaking scope into smaller, more manageable pieces — the engine behind the...
Definition of Done (DoD)
AgileThe Definition of Done is the team's shared, explicit checklist of what "complete" means for every increment —...
Definition of Ready
AgileThe definition of ready is the team's checklist for backlog items entering a sprint: clear enough, small enoug...
Deliverable
FundamentalsA deliverable is any unique, verifiable product, result, or capability a project must produce — tangible (a bu...
Delphi Technique
PlanningThe Delphi technique gathers expert judgment anonymously and in rounds: experts answer independently, a facili...
Dependency Types (FS, SS, FF, SF)
ScheduleFour logical relationships link activities: Finish-to-Start (successor starts after predecessor finishes — 90%...
Design of Experiments (DOE)
QualityDesign of experiments is the statistical method for testing multiple factors simultaneously to find which ones...
Design Thinking
AgileDesign thinking is a human-centered problem-solving cycle: empathize with users, define the real problem, idea...
Development Team (Developers)
AgileThe development team — current Scrum Guide just says "developers" — is everyone who builds the increment: engi...
DevOps
EngineeringDevOps collapses the wall between development ("change fast") and operations ("stay stable") into one culture...
Disbenefit
ProgramA disbenefit is a genuinely negative outcome a program creates for some stakeholder as a consequence of succee...
DSDM (Dynamic Systems Development Method)
AgileDSDM is one of agile's elders (1994), distinctive for wrapping iterative delivery in full project governance:...
Duration vs Effort
ScheduleEffort is the labor content (40 person-hours); duration is the calendar time it occupies (could be 1 day with...
E
Earned Value (EV)
EVM & CostEarned Value is the budgeted worth of the work actually completed — not what you spent, but what the finished...
Earned Value Management (EVM)
EVM & CostEarned Value Management is the technique that answers the question every sponsor eventually asks: "You've spen...
Emergent Risk
RiskEmergent risks are the ones that couldn't have been identified in advance — unknowable unknowns arising from c...
Emotional Intelligence (EI)
LeadershipEmotional intelligence is the ability to recognize and manage your own emotions and to read and respond to oth...
Enterprise Environmental Factors (EEFs)
FundamentalsEnterprise environmental factors are the conditions around your project that you don't control but must plan w...
Enterprise Risk Management (ERM)
RiskERM manages risk at the whole-organization level — strategic, financial, operational, reputational, compliance...
Epic
AgileAn epic is a body of work too large to finish in one sprint — a container that gets progressively broken into...
Escalation (Escalation Path)
GovernanceEscalation is deliberately moving an issue, risk, or decision to a higher authority because it exceeds your ow...
Estimate at Completion (EAC)
EVM & CostEstimate at Completion is the forecast of what the whole project will actually cost, given performance so far....
Estimate to Complete (ETC)
EVM & CostEstimate to Complete answers the forward-looking question: "from this point, how much more money do we need to...
Expected Monetary Value (EMV)
RiskExpected monetary value converts an uncertain event into a single planning number: probability × impact. Threa...
Expert Judgment
PlanningExpert judgment means consulting people with relevant specialized knowledge — team members, consultants, other...
Extreme Programming (XP)
AgileXP is the agile method with the strongest engineering opinions: pair programming, test-driven development, con...
F
Fallback Plan
RiskThe fallback plan is plan C: what you execute if the risk occurs and the primary response (the contingency pla...
Fast Tracking
ScheduleFast tracking compresses the schedule by performing activities in parallel that were planned in sequence. It c...
Feasibility Analysis
BusinessA feasibility analysis tests whether a proposed project can realistically succeed before serious money commits...
Feature
AgileA feature is a coherent chunk of product capability that delivers value a user can recognize — bigger than a s...
Feature-Driven Development (FDD)
AgileFDD is an agile method built around a features list: develop an overall object model, list the features (small...
Fishbone Diagram (Ishikawa)
QualityThe fishbone (Ishikawa, cause-and-effect) diagram puts one problem at the fish's head and organizes potential...
Fixed Formula Method (50/50 Rule)
CostThe fixed formula method credits earned value in preset chunks: 50/50 (half when the activity starts, half at...
Fixed-Price Contract
ProcurementIn a fixed-price (lump sum) contract, the seller commits to deliver defined scope for a set price — and eats a...
Float (Slack)
ScheduleFloat (also called slack) is how long an activity can be delayed without pushing the project's finish date. Ac...
Forward Pass & Backward Pass
ScheduleThe forward pass walks the network left to right computing each activity's earliest start and finish; the back...
Free Float
ScheduleFree float is the tighter cousin of total float: how long an activity can slip without delaying the early star...
Functional Organization
OrganizationIn a functional organization, staff are grouped by specialty — engineering, marketing, finance — and report to...
G
Gantt Chart
ScheduleA Gantt chart is the horizontal bar chart of the schedule: each activity is a bar placed on a calendar, its le...
Generalizing Specialist (T-Shaped)
AgileA generalizing specialist — the T-shaped person — has deep expertise in one discipline (the T's stem) plus wor...
Gold Plating
ScopeGold plating is adding features or polish the customer never asked for — extra scope injected by the team itse...
Governance Tolerance Range
GovernanceA governance tolerance range defines the acceptable limits of variation — in cost, schedule, scope, or quality...
Grade vs Quality
QualityGrade is a category of features — economy versus premium. Quality is how well the thing meets its requirements...
H
Hard Dependency (Mandatory Dependency)
ScheduleA hard (mandatory) dependency is a sequence you cannot change because physics, law, or the nature of the work...
Histogram
QualityA histogram is a bar chart of a distribution: values grouped into bins, bar height showing frequency. Its gift...
Hybrid Approach
FundamentalsA hybrid approach mixes predictive and adaptive methods within one project: typically predictive where scope i...
I
Impact Mapping
AgileImpact mapping draws a four-level tree from goal to backlog: Why (the measurable goal) → Who (actors who can m...
Impediment (Blocker)
AgileAn impediment is anything slowing or stopping the team's progress: a blocked dependency, a missing decision, a...
Increment
AgileThe increment is the sum of all backlog items completed during a sprint plus all prior increments — a concrete...
Incremental Value Delivery
ValueIncremental value delivery means releasing usable value in slices throughout the project instead of one big ba...
Influence Diagram
RiskAn influence diagram is a compact graph of a decision situation: decisions (squares), uncertainties (circles),...
Information Radiator
AgileAn information radiator is a large, always-visible display of project truth — task board, burndown, build stat...
Integrated Change Control
IntegrationIntegrated change control is the discipline of reviewing every change request, assessing its impact across all...
Internal Rate of Return (IRR)
BusinessIRR is the discount rate at which a project's NPV equals exactly zero — effectively the project's implied annu...
Issue Log
MonitoringThe issue log tracks problems that have already happened and need resolution: each issue gets an owner, a prio...
Iteration
AgileAn iteration is a fixed-length development cycle — plan a slice, build it, review it, improve the process, rep...
Iterative vs Incremental Development
AgileIncremental delivers finished pieces one at a time — each increment is done, but the product grows part by par...
K
Kaizen (Continuous Improvement)
LeanKaizen — Japanese for "change for the better" — is the practice of relentless, small, everyone-driven improvem...
Kanban
AgileKanban is a flow-based method: visualize the work on a board, limit how much is in progress at once, and conti...
Kanban Board
AgileA kanban board visualizes workflow: columns for each state (to do → in progress → review → done), cards for wo...
Key Performance Indicator (KPI)
MonitoringA KPI is a measurable value tracking progress toward an objective that matters — emphasis on key: a handful ch...
Kickoff Meeting
IntegrationThe kickoff meeting marks the start of execution: it brings the team and key stakeholders together to align on...
Kill Point
GovernanceA kill point is a phase gate viewed from its sharpest angle: the pre-agreed moment where the project can be te...
L
Lead Time
AgileLead time is the clock the customer sees: from the moment work is requested to the moment it's delivered — que...
Leads and Lags
ScheduleA lead accelerates a successor activity — it starts before its predecessor finishes (shown as a negative value...
Lean Software Development (Seven Wastes)
LeanLean software development (the Poppendiecks' translation of Toyota principles) centers on eliminating waste —...
Lessons Learned
GeneralLessons learned is the discipline of capturing what worked and what didn't — throughout the project, not just...
Level of Effort, Discrete & Apportioned Effort
CostEarned value recognizes three work types: discrete effort — measurable, tied to specific deliverables (pour 10...
M
Make-or-Buy Analysis
ProcurementMake-or-buy analysis is the structured decision between producing something in-house and procuring it: compare...
Management Reserve
RiskManagement reserve is budget or schedule held for the truly unforeseen — the "unknown unknowns" no risk worksh...
Management Reserve (Program)
FinanceA management reserve at the program level is a budget set aside to handle unknown-unknown risks — events that...
Matrix Organization
OrganizationA matrix blends functional and projectized structures: people keep a functional home (and boss) while also ans...
Methodology
FundamentalsA methodology is a defined system of practices, techniques, procedures, and rules for running projects — PRINC...
Milestone
ScheduleA milestone is a significant point or event in the project — a phase gate passed, a major deliverable accepted...
Mind Mapping
PlanningMind mapping radiates ideas from a central concept outward into branches and sub-branches, capturing structure...
Minimum Viable Product (MVP)
AgileAn MVP is the smallest version of a product that delivers real value to real users while maximizing what the t...
Mob Programming
EngineeringMob programming is the whole team working on one problem at one screen: a single driver types (rotating every...
Monte Carlo Simulation
RiskMonte Carlo simulation is a quantitative risk technique that runs a project model thousands of times with rand...
MoSCoW Prioritization
AgileMoSCoW sorts requirements into four buckets: Must have (without these, the release fails or is illegal), Shoul...
Motivation Theories (Maslow, Herzberg, McGregor)
LeadershipThe exam's big three: Maslow's hierarchy — needs stack from physiological through safety, social, and esteem t...
Multicriteria Decision Analysis (Weighted Scoring)
PlanningMulticriteria decision analysis evaluates options against several weighted criteria in a matrix: define criter...
N
Near-Critical Path
ScheduleA near-critical path is a chain of activities with float so small that a modest slip makes it the new critical...
Net Present Value (NPV)
BusinessNPV discounts every future cash flow back to today's money and subtracts the investment: money later is worth...
Nominal Group Technique
PlanningNominal group technique structures brainstorming to protect it from its own dynamics: ideas are generated sile...
O
OKRs (Objectives and Key Results)
BusinessOKRs pair a qualitative, inspiring Objective ("make onboarding effortless") with 3–5 measurable Key Results th...
Operational Readiness
ProgramOperational readiness is the verified state where the receiving organization can actually run what's being del...
Opportunity (Positive Risk)
RiskAn opportunity is a risk with an upside — an uncertain event that would help objectives if it occurred. It get...
Organizational Breakdown Structure (OBS)
ResourceThe OBS is the hierarchical chart of the project organization — departments, teams, units — arranged so work c...
Organizational Change Management (OCM)
IntegrationOCM prepares people to adopt what projects deliver: stakeholder readiness, communication, training, champions,...
Organizational Change Management (Program)
StrategyOrganizational change management at the program level is the discipline of preparing, supporting, and guiding...
Organizational Process Assets (OPAs)
FundamentalsOrganizational process assets are everything your organization has learned and standardized that you can reuse...
Osmotic Communication
AgileOsmotic communication (Alistair Cockburn, Crystal) is the useful information team members absorb from backgrou...
Output vs Outcome
FundamentalsAn output is what the project produces — the system, the building, the report. An outcome is the changed condi...
Overall Project Risk
RiskOverall project risk is the uncertainty of the project as a whole — the combined effect of all individual risk...
P
Pacing (Program)
ProgramPacing is deliberately timing component starts, finishes, and outputs so the program flows: benefits arrive wh...
Pair Programming
EngineeringPair programming puts two developers on one problem at one screen: the driver types, the navigator reviews con...
Parametric Estimating
CostParametric estimating multiplies a unit rate by a quantity: cost per square meter × square meters, hours per t...
Pareto Chart
QualityA Pareto chart is a bar chart of problem causes sorted from most to least frequent, usually with a cumulative-...
Path Convergence & Divergence
SchedulePath convergence is multiple network paths merging into one activity — that node needs all of them finished, s...
Payback Period
BusinessThe payback period is how long an investment takes to earn back its initial cost — the simplest project-select...
Performance Measurement Baseline (PMB)
CostThe PMB is the integrated scope-schedule-cost baseline that earned value measures against: the WBS says what,...
Performing Organization
OrganizationThe performing organization is the enterprise whose people actually do the project work — the contractor build...
Persona
AgileA persona is a fictional but research-grounded archetype of a user — name, role, goals, frustrations, context...
PESTLE Analysis
PlanningPESTLE scans the macro environment across six lenses: Political, Economic, Social, Technological, Legal, Envir...
Phase Gate (Stage Gate)
GovernanceA phase gate is a formal checkpoint at a phase's end where governance reviews performance and the business cas...
Phase-Gate Review
GovernanceA phase-gate review is a formal decision point in a program's life cycle where the program's governance board...
Plan-Do-Check-Act (PDCA)
QualityPDCA — the Shewhart/Deming cycle — is the engine of continuous improvement: Plan a change with a predicted out...
Planned Value (PV)
EVM & CostPlanned Value is the authorized budget for the work scheduled to be done by a given date — in plain terms, "wh...
Planning Poker
AgilePlanning poker is consensus-based estimation: each team member privately picks a card (usually Fibonacci — 1,...
PMBOK Guide
FundamentalsThe PMBOK® Guide is PMI's foundational standard for project management. The 7th edition (2021) reframed it aro...
PMP Exam 2026: What's New
ExamThe 2026-era PMP continues three domains — People, Process, Business Environment — with roughly half of questi...
Portfolio Balancing
OrganizationPortfolio balancing is the ongoing act of tuning the investment mix — risk versus return, short-term versus st...
Portfolio Management
OrganizationPortfolio management selects and balances the organization's whole collection of projects and programs against...
Power/Interest Grid
GeneralThe power/interest grid classifies stakeholders along two axes — their power over the project and their intere...
Precedence Diagram Method (Network Diagram)
ScheduleThe precedence diagram method (PDM) draws the schedule as a network: activities are boxes, dependencies are ar...
Precision vs Accuracy
QualityAccuracy means close to the true value; precision means measurements cluster tightly together. They're indepen...
Predictive Life Cycle (Waterfall)
FundamentalsA predictive (plan-driven, waterfall) life cycle fixes scope, schedule, and cost early, then executes phase by...
Probability and Impact Matrix
RiskThe probability-impact (P×I) matrix is the grid that turns qualitative risk scores into priorities: probabilit...
Process Groups (IPECC)
FundamentalsThe five process groups — Initiating, Planning, Executing, Monitoring & Controlling, Closing (IPECC) — organiz...
Procurement Audit
ProcurementA procurement audit is the structured review of the procurement process itself — from planning through contrac...
Procurement Documents (RFP, RFQ, IFB)
ProcurementThe three bid documents map to what the buyer knows: RFQ (request for quotation) — commodity purchase, price i...
Procurement Management Plan
ProcurementThe procurement management plan defines how the project will buy: what gets procured versus made, contract typ...
Product Backlog
AgileThe product backlog is the single, ordered list of everything that might be built — features, fixes, improveme...
Product Life Cycle
FundamentalsThe product life cycle spans a product's whole existence — introduction, growth, maturity, decline, retirement...
Product Owner
AgileThe product owner owns the what and the why: maximizing product value by managing and ordering the product bac...
Product Roadmap
AgileA product roadmap communicates direction over time: themes and outcomes now / next / later — deliberately coar...
Product Scope vs Project Scope
ScopeProduct scope is the features and functions of the thing being delivered; project scope is all the work requir...
Program Audits & Compliance
GovernanceProgram audits are independent examinations of whether the program follows its governance, manages money and r...
Program Change Management
ProgramAt program level, change management means two linked things: controlling changes to program scope, roadmap, an...
Program Charter
ProgramThe program charter authorizes the program: its vision, intended benefits, scope at program level, key compone...
Program Closure
ProgramProgram closure is the final phase: confirm remaining benefits are transitioned to sustainment owners, close o...
Program Collaboration
TeamCollaboration in program management means creating the conditions where component teams, the program core team...
Program Contingency Reserve
FinanceA program contingency reserve is budget set aside at the program level to cover the financial impact of identi...
Program Core Team
TeamThe program core team is the group of senior professionals who work directly with the program manager to plan,...
Program Definition Phase (Formulation & Planning)
ProgramProgram definition is the first life-cycle phase, in two movements: formulation — shape the business case, sec...
Program Financial Framework
ProgramThe program financial framework defines how money flows through the program: funding sources and their timing,...
Program Formulation
Life CycleProgram formulation is the first sub-phase within the program definition phase, where the program's basic stru...
Program Governance
ProgramProgram governance is the framework of oversight: the governance board, phase-gate reviews, escalation thresho...
Program Infrastructure Development
IntegrationProgram infrastructure development is the process of establishing the foundational structures, tools, processe...
Program Integration Management
ProgramProgram integration management coordinates everything that crosses component boundaries: interdependencies, sh...
Program Life Cycle
ProgramPMI's program life cycle has three phases: definition (build the business case, charter, and roadmap), deliver...
Program Management
ProgramProgram management coordinates a group of related projects (and other work) as one entity to capture benefits...
Program Manager vs Project Manager
ProgramThe project manager delivers defined scope on time and budget; the program manager delivers benefits through m...
Program Master Schedule
ScheduleThe program master schedule is the high-level schedule that shows how all of a program's component projects an...
Program Performance Baseline
PerformanceThe program performance baseline is the approved, integrated reference point for measuring program performance...
Program Procurement Management
ProcurementProgram procurement management covers how a program plans, executes, and controls the acquisition of goods and...
Program Resource Management Plan
ResourcesThe program resource management plan defines how resources — people, equipment, budget, and materials — will b...
Program Risk Thresholds
ProgramProgram risk thresholds are the quantified limits that define which risks belong at which level: below the lin...
Program Roadmap
ProgramThe program roadmap is the chronological big picture: components, major milestones, key dependencies, and — cr...
Program Sponsor
GovernanceThe program sponsor is the senior executive or organizational leader who champions the program at the highest...
Program Stakeholder Engagement
ProgramProgram stakeholder engagement manages a landscape wider and more political than any project's: executives, re...
Program Vision
ProgramThe program vision is the concise picture of the future state the program exists to create — vivid enough to a...
Program Work Breakdown Structure (PWBS)
ProgramThe program WBS decomposes the program to the level where components take over: program-level deliverables, th...
Progressive Elaboration
FundamentalsProgressive elaboration is the principle that project plans get continuously more detailed and accurate as bet...
Project Calendar
ScheduleThe project calendar defines when project work may happen — working days, shifts, holidays, seasonal windows —...
Project Charter
IntegrationThe project charter is the document that formally authorizes a project to exist and names the project manager....
Project Governance
GovernanceProject governance is the oversight framework around a project: who approves what, how decisions above the PM'...
Project Life Cycle
FundamentalsThe project life cycle is the series of phases a project passes through from start to close — commonly startin...
Project Management Information System (PMIS)
IntegrationThe PMIS is the integrated tool environment the project runs on: scheduling software, cost tracking, document...
Project Management Office (PMO)
OrganizationA PMO standardizes project governance and supports project managers. PMI's three types by control level: suppo...
Project Management Plan
IntegrationThe project management plan is the master playbook: how the project will be executed, monitored, and closed. I...
Project Phase
FundamentalsA project phase is a collection of logically related activities culminating in the completion of one or more d...
Project Scope Statement
ScopeThe scope statement describes, in writing, what the project will deliver and — just as important — what it won...
Project Sponsor
StakeholderThe sponsor is the person (or group) who provides the money and the political air cover, champions the project...
Project Success Criteria
FundamentalsProject success is multi-layered and must be defined before delivery starts: project management success (scope...
Projectized Organization
OrganizationIn a projectized organization, the project is the primary structure: teams are dedicated, colocated around the...
Projects vs Operations
FundamentalsA project is temporary and unique: it has a start, an end, and produces something that didn't exist. Operation...
Prompt List (PESTLE, TECOP, VUCA)
RiskA prompt list is a predetermined set of risk categories used to systematically jog identification — walk each...
Psychological Safety
TeamPsychological safety is the shared belief that the team is safe for interpersonal risk — you can ask the naive...
Q
Qualitative Risk Analysis
RiskQualitative risk analysis ranks the risk register fast: each risk is scored on probability and impact (high/me...
Quality Assurance (QA)
QualityQuality assurance is process-focused and preventive: it asks "are we working in a way that will produce good d...
Quality Audit
QualityA quality audit is a structured, usually independent review of whether project activities comply with organiza...
Quality Control (QC)
QualityQuality control is product-focused and detective: it inspects, measures, and tests actual deliverables against...
Quantitative Risk Analysis
RiskQuantitative risk analysis puts real numbers on the top-priority risks: Monte Carlo simulation for schedule/co...
R
RACI Chart
GeneralA RACI chart maps every activity to who is Responsible (does the work), Accountable (owns the outcome — exactl...
Refactoring
EngineeringRefactoring improves code's internal structure without changing its external behavior — renaming for clarity,...
Release Planning
AgileRelease planning maps backlog to time at the medium range: which features land in which release, driven by eit...
Requirements Elicitation
BusinessElicitation is actively drawing requirements out of stakeholders and sources — interviews, workshops, observat...
Requirements Traceability Matrix (RTM)
ScopeThe requirements traceability matrix is a table linking every requirement to its origin (business need, stakeh...
Reserve Analysis
CostReserve analysis sizes and then monitors the project's buffers: contingency reserve for identified risks (insi...
Residual Risk
RiskResidual risk is what's left after a risk response is implemented. Mitigation reduces a risk; it rarely erases...
Resource Breakdown Structure (RBS)
ResourceThe resource breakdown structure is a hierarchical view of resources by category and type — labor (by trade an...
Resource Calendar
ResourceA resource calendar shows when each specific resource — a person, a crane, a test lab — is actually available...
Resource Histogram
ResourceA resource histogram is a bar chart of resource demand over time — hours or headcount per week, stacked by rol...
Resource Leveling
ResourceResource leveling adjusts the schedule to resolve overallocation — when the plan needs a person or machine in...
Resource Smoothing
ResourceResource smoothing evens out resource demand by shifting activities only within their available float — peaks...
Responsibility Assignment Matrix (RAM)
ResourceA responsibility assignment matrix maps work (rows) to people or roles (columns) so every piece of work has ex...
Retrospective
AgileThe retrospective is the recurring meeting — end of every sprint — where the team inspects its own process: wh...
Return on Investment (ROI)
BusinessROI expresses net benefit as a percentage of cost: what did each invested dollar give back? It's the most wide...
Rework
QualityRework is doing work again because it wasn't right the first time — the purest form of internal failure cost a...
Risk Appetite
RiskRisk appetite is how much uncertainty an organization is willing to accept in pursuit of its objectives — a st...
Risk Appetite, Tolerance & Threshold
RiskThree nested dials: appetite is the general disposition — how much uncertainty the organization is willing to...
Risk Audit & Risk Reassessment
RiskTwo distinct check-ups: a risk reassessment re-examines the risks themselves — new ones identified, stale ones...
Risk Breakdown Structure (RBS)
RiskThe risk breakdown structure is a hierarchical chart of risk categories — technical, external, organizational,...
Risk Burndown Chart
RiskA risk burndown chart plots total risk exposure (sum of probability × impact across the register) over time —...
Risk Categories
RiskRisk categories group risks by source — technical, external, organizational, project-management (the classic R...
Risk Data Quality Assessment
RiskRisk data quality assessment checks how trustworthy the information behind each risk rating is — accuracy, rel...
Risk Exposure
RiskRisk exposure is the quantified amount of risk carried — for one risk, probability × impact (its EMV); for a p...
Risk Management Plan
RiskThe risk management plan defines how risk will be managed on this project — methodology, roles, categories (th...
Risk Owner
RiskThe risk owner is the single named person accountable for monitoring a specific risk and executing its respons...
Risk Register
RiskThe risk register is the living log of identified risks: each entry with its description, probability, impact,...
Risk Response Strategies
RiskFor threats there are five responses: avoid (eliminate the risk by changing the plan), mitigate (reduce probab...
Risk Threshold
RiskA risk threshold is the measurable line drawn from risk appetite — the specific level of exposure above which...
Risk Trigger (Trigger Condition)
RiskA risk trigger is the observable warning sign that a risk is about to occur or has begun — the tripwire that a...
Rolling Wave Planning
PlanningRolling wave planning means planning near-term work in detail and leaving far-future work at a higher level, e...
S
S-Curve
CostThe S-curve is cumulative cost (or work) plotted over time. It's S-shaped because projects spend slowly at fir...
SAFe (Scaled Agile Framework)
ScalingSAFe is the most widely adopted framework for running agile across many teams: Agile Release Trains (5–12 team...
Salience Model
StakeholderThe salience model classifies stakeholders on three attributes: power (can they impose their will?), legitimac...
Scatter Diagram
QualityA scatter diagram plots two variables against each other, one dot per observation, to reveal whether they move...
Schedule Baseline
ScheduleThe schedule baseline is the approved version of the schedule — the fixed reference that actual progress is me...
Schedule Performance Index (SPI)
EVM & CostSPI measures schedule efficiency: the rate at which work is actually being completed versus the rate the plan...
Schedule Variance (SV)
EVM & CostSchedule Variance expresses schedule position in dollars: the value of work completed minus the value of work...
Scope Baseline
ScopeThe scope baseline is the approved definition of what the project will deliver: the scope statement, the WBS,...
Scope Creep
ScopeScope creep is the uncontrolled growth of project scope — additions that bypass change control, arriving one "...
Scrum
AgileScrum is the most widely used agile framework: small cross-functional teams deliver working product in fixed-l...
Scrum Master
AgileThe scrum master is the team's servant-leader and process guardian: coaching Scrum practice, removing impedime...
Scrum of Scrums
ScalingScrum of scrums scales coordination: each team sends a representative to a regular cross-team standup focused...
Secondary Risk
RiskA secondary risk is a brand-new risk created by your risk response itself. You fixed one problem and your fix...
Self-Organizing Team
AgileA self-organizing team decides internally how to accomplish its work — who takes what, how to solve problems,...
Sensitivity Analysis (Tornado Diagram)
RiskSensitivity analysis asks: which input uncertainties move the outcome most? Vary one factor at a time across i...
Servant Leadership
LeadershipServant leadership inverts the traditional pyramid: the leader's job is to serve the team — removing impedimen...
Siloed Organization
OrganizationA siloed organization groups people by specialty — analysis, development, testing, operations — so value must...
Smoke Testing
EngineeringA smoke test is the fast sanity check that a build's vital functions work at all — can it start, log in, load...
Source Selection Criteria
ProcurementSource selection criteria are the published, weighted factors used to score seller proposals: technical approa...
Spike
AgileA spike is a timeboxed investigation whose deliverable is knowledge, not product: research a technology, proto...
Sprint
AgileA sprint (or iteration) is a short, fixed-length timebox — commonly two weeks — in which the team plans, build...
Sprint Backlog
AgileThe sprint backlog is the developers' plan for the sprint: the sprint goal, the product backlog items selected...
Sprint Planning
AgileSprint planning opens each sprint: the team answers why (craft a sprint goal), what (select backlog items the...
Sprint Review
AgileThe sprint review closes the sprint's product loop: the team demonstrates the working increment to stakeholder...
Stakeholder
StakeholderA stakeholder is any individual, group, or organization that can affect, be affected by, or merely perceive it...
Stakeholder Analysis
StakeholderStakeholder analysis systematically works out who your stakeholders are, what they want, how much they matter,...
Stakeholder Engagement Assessment Matrix
StakeholderThis matrix compares each stakeholder's current engagement level against the level you need: unaware, resistan...
Stakeholder Engagement Plan
StakeholderThe stakeholder engagement plan turns analysis into strategy: for each key stakeholder or group, the desired e...
Stakeholder Register
GeneralThe stakeholder register is the catalog of everyone who can affect or be affected by the project — with their...
Statement of Work (SOW)
ProcurementThe statement of work is the narrative description of the products, services, or results to be delivered — in...
Steering Committee (Governance Board)
ProgramThe steering committee (program governance board) is the senior group that owns the big decisions: approving t...
Story Points
AgileStory points are a relative, unitless measure of effort — this item is roughly twice that one — covering compl...
Strategic Alignment
ProgramStrategic alignment is the continuous fit between a program and the organization's strategy — checked at initi...
Subprogram
FundamentalsA subprogram is a group of related projects and activities within a larger program that are managed together b...
Subsidiary Management Plans
IntegrationThe project management plan is a binder of subsidiary plans, one per discipline: scope, requirements, schedule...
Summary Activity (Hammock)
ScheduleA summary (hammock) activity is a single bar representing a group of related activities — its dates and durati...
Sunk Cost
BusinessA sunk cost is money already spent and unrecoverable — and therefore, rationally, irrelevant to any decision a...
Sustainability in Project Management (ESG)
EmergingSustainability in projects means managing environmental, social, and governance impact as first-class constrai...
Swarming
AgileSwarming is the whole team (or most of it) converging on one work item to finish it before starting anything e...
SWOT Analysis
RiskSWOT examines a project or decision from four angles: internal Strengths and Weaknesses, external Opportunitie...
Synergy (Program)
ProgramSynergy is the extra value created when components are managed together — benefits unavailable to the same pro...
T
Tailoring
FundamentalsTailoring is deliberately selecting which processes, methods, and artifacts fit this project — instead of runn...
Team Charter & Ground Rules
TeamThe team charter is the team's social contract, written by the team itself: values, working agreements, commun...
Team of Teams
TeamTeam of teams is a program management principle introduced in the 5th edition of the PMI Standard for Program...
Technical Debt
EngineeringTechnical debt is the accumulated future cost of past shortcuts — quick hacks, skipped tests, outdated depende...
Test Plan
QualityA test plan defines how deliverables will be verified: what gets tested at which levels (unit, integration, sy...
Test-Driven Development (TDD)
EngineeringTDD inverts the usual order: write a failing test first (red), write the minimum code to pass it (green), then...
Three-Point Estimating (PERT)
CostThree-point estimating replaces a single guess with three: optimistic (O), most likely (M), and pessimistic (P...
Throughput
AgileThroughput is the count of work items finished per time period — ten stories a week, forty tickets a month. Wi...
Time and Materials (T&M) Contract
ProcurementA time and materials contract pays for hours worked at agreed rates plus materials at cost — a hybrid sitting...
Timeboxing
AgileTimeboxing fixes the time and lets the content flex: the meeting is 15 minutes, the sprint is 2 weeks, the spi...
To-Complete Performance Index (TCPI)
EVM & CostTCPI is the efficiency the project must achieve on all remaining work to finish within a target budget — essen...
Total Cost of Ownership (TCO)
BusinessTotal cost of ownership is the full life-cycle price of an option: acquisition plus operation, maintenance, tr...
Trend & Regression Analysis
MonitoringTrend analysis reads performance over time — CPI drifting down for three periods says more than any single val...
Triple Constraint (Iron Triangle)
FundamentalsThe triple constraint — scope, time, cost, with quality living in the middle — says the three sides are linked...
Tuckman Ladder (Team Development Stages)
TeamTuckman's model says teams develop through five stages: forming (polite, uncertain, leader-dependent), stormin...
U
Use Case
BusinessA use case describes how an actor (user, system, or time trigger) interacts with a system to achieve a goal —...
User Acceptance Testing (UAT)
AgileUAT is real users (or their representatives) verifying the system supports their actual work before go-live —...
User Experience (UX)
AgileUser experience is the totality of how it feels to use the product — findability, speed, clarity, error recove...
User Story
AgileA user story is a small, plain-language statement of need from the user's perspective — classically "As a [rol...
User Story Mapping
AgileStory mapping (Jeff Patton) arranges the backlog in two dimensions: the user's journey flows left to right (th...
V
Validate Scope
ScopeValidate Scope is the customer formally accepting completed deliverables. Its exam twin, Control Quality, is t...
Value Delivery
ValueValue delivery is the through-line of the modern PMP exam: projects exist to deliver value — to customers, the...
Value Delivery System (PMBOK 7)
ValueThe value delivery system is PMBOK 7's big frame: portfolios, programs, projects, products, and operations wor...
Value Proposition
BusinessA value proposition states why someone should choose this — the specific benefit, for a specific audience, ver...
Value Realization
ValueValue realization is value actually arriving — measured, in the books, in the mission — as opposed to value pr...
Value Stream Mapping
LeanValue stream mapping draws every step from request to delivered value, timing each one and — crucially — the w...
Value-Based Prioritization
ValueValue-based prioritization orders work by value contribution — economic (revenue, savings, cost of delay), ris...
Variance Analysis
MonitoringVariance analysis compares actual performance to baseline, quantifies the gap (cost variance, schedule varianc...
Variance at Completion (VAC)
EVM & CostVariance at Completion is the projected difference between the original budget and the forecast final cost — t...
Velocity
AgileVelocity is the amount of work (usually story points) a team actually completes per sprint, averaged over rece...
Verification vs Validation
QualityVerification asks: did we build the thing right — does it conform to specifications and requirements? (Interna...
Virtual Teams
TeamVirtual teams work toward shared goals with little or no face time — distributed across cities, countries, and...
W
Watch List
RiskThe watch list holds low-priority risks — scored too small for active responses but too real to delete. They g...
WBS Dictionary
ScopeThe WBS dictionary is the companion document to the work breakdown structure: for each WBS element it spells o...
What-If Scenario Analysis & Simulation
RiskWhat-if scenario analysis tests the plan against specific hypotheticals — what if the permit slips 60 days? wh...
WIP Limits
AgileWork-in-progress limits cap how many items can occupy a workflow stage at once. They feel counterintuitive — l...
Work Breakdown Structure (WBS)
ScopeThe WBS is a hierarchical decomposition of the total project scope into smaller, manageable pieces — everythin...
Work Package
ScopeA work package is the lowest level of the WBS — a chunk of work small enough to be reliably estimated for cost...
Work Performance Data, Information & Reports
MonitoringPMI's refinement chain: data are raw observations (12 defects, 47% complete, $89K spent); information is data...
Workaround
RiskA workaround is the response to a risk that was never planned for — an unidentified risk (or a passively accep...
No matching terms. Try a different word.