ExamArmor Reference

The Complete AWS Cloud Computing Glossary

Master the essential vocabulary and exam context for the AWS Solutions Architect Associate, Cloud Practitioner, Developer Associate, and DevOps Engineer Professional certifications.

A

Acceptance Criteria

Scope

Acceptance criteria are the specific, testable conditions a deliverable must meet before the customer accepts...

Acceptance-Test-Driven Development (ATDD)

Engineering

ATDD writes the acceptance tests collaboratively — customer, developer, tester together — before development b...

Accountability vs Responsibility

Team

Accountability is answering for the outcome — it belongs to exactly one person and cannot be shared or delegat...

Activity

Schedule

An activity is a distinct, scheduled piece of work with a duration, resources, and usually dependencies — the...

Actual Cost (AC)

EVM & Cost

Actual Cost is the simplest of the three EVM numbers: the total money actually spent to accomplish the work co...

Adaptive Life Cycle (Agile)

Fundamentals

An adaptive (agile, change-driven) life cycle fixes time and cost into short iterations and lets scope flex: b...

Affinity Diagram

Planning

An affinity diagram organizes a large messy set of ideas into natural clusters: everyone writes items on cards...

Agile Coach

Agile

An agile coach develops agile capability beyond a single team — coaching teams, leaders, and the organization...

Agile Manifesto

Agile

The 2001 Agile Manifesto states four value pairs: individuals and interactions over processes and tools, worki...

Agile Mindset

Agile

The agile mindset is the belief system beneath the practices: value flows from learning fast, people closest t...

AI Ethics & Governance in Projects

Emerging

When projects use or deliver AI, governance questions become project management questions: data privacy (what...

AI in Project Management

Emerging

AI in project management spans machine assistance across the life cycle: schedule risk prediction from histori...

AI-Augmented Project Management (PMP 2026)

Emerging

The 2026 PMP expects working literacy in AI as a PM tool: predictive analytics (schedule/cost risk forecasts f...

Alternatives Analysis

Planning

Alternatives analysis is the structured comparison of different ways to achieve an objective — build vs buy vs...

Analogous Estimating

Cost

Analogous (top-down) estimating prices new work by comparing it to similar past work, adjusted for differences...

Artifact

Fundamentals

An artifact is any document, template, output, or deliverable produced while managing a project — charters, re...

Assumption Log

Planning

The assumption log records what you're treating as true without proof (assumptions) and what you must work wit...

B

Backlog Refinement (Grooming)

Agile

Backlog refinement is the ongoing activity of keeping the backlog ready: splitting epics into stories, clarify...

Behavior-Driven Development (BDD)

Engineering

BDD extends TDD by writing examples of system behavior in business-readable language — Given/When/Then — agree...

Benchmarking

Quality

Benchmarking compares your practices, processes, or metrics against comparable projects or organizations — int...

Benefits Delivery Phase

Benefits Management

The benefits delivery phase is the period in a program's life cycle when component projects and program activi...

Benefits Identification

Benefits Management

Benefits identification is the first phase of program benefits management — the process of figuring out exactl...

Benefits Management Plan

Program

The benefits management plan defines each intended benefit, how and when it will be measured, who owns it, and...

Benefits Realization

Program

Benefits realization is the discipline of ensuring a project or program actually produces the business value t...

Benefits Register

Program

The benefits register lists every planned benefit with its measure, baseline, target, timing, owner, and curre...

Benefits Sustainment Plan

Benefits Management

A benefits sustainment plan is the document that defines how the benefits delivered by a program will be maint...

Benefits Transition & Sustainment

Program

Benefits transition hands delivered capabilities to the operational owners who will run them; sustainment ensu...

Bidder Conference

Procurement

A bidder conference is the meeting where all prospective sellers hear the buyer's requirements and ask questio...

Bottom-Up Estimating

Cost

Bottom-up estimating prices every work package individually — ideally with the people who'll do the work — the...

Budget at Completion (BAC)

EVM & Cost

Budget at Completion is the total authorized budget for the entire project — the finish-line number all other...

Burndown Chart

Agile

A burndown chart plots remaining work (story points, hours, or tasks) against time, falling toward zero as a s...

Burnup Chart

Agile

A burnup chart plots completed work rising toward a total-scope line over time. Unlike the burndown, it shows...

Business Analysis

Business

Business analysis is the discipline of identifying business needs and defining solutions that deliver value —...

Business Case

Program

The business case is the document that justifies the investment: the problem or opportunity, the options consi...

Business Need & Business Objective

Business

The business need is the problem or opportunity that justifies doing anything at all — falling retention, a ne...

Business Value

Business

Business value is the net benefit an initiative creates — tangible (revenue, cost savings, market share) and i...

C

Cadence

Agile

Cadence is the rhythm work runs on — the fixed heartbeat of sprints, releases, planning, and reviews. A steady...

Capability

Program

A capability is the organizational capacity to do something it couldn't before — run same-day fulfillment, und...

Change Control Board (CCB)

Scope

The Change Control Board is the group with the authority to approve, defer, or reject change requests — typica...

Change Control System

Integration

The change control system is the machinery that executes the change management plan: the forms, the tracking t...

Change Management Plan

Integration

The change management plan defines how changes will be handled before any change exists: who may submit reques...

Change Request

Integration

A change request is the formal proposal to modify any project document, deliverable, or baseline. Four flavors...

Claims Administration

Procurement

Claims administration is the process of documenting, monitoring, and resolving contested changes — situations...

Code of Accounts

Cost

The code of accounts is the numbering system that uniquely identifies every WBS element (1.2.3 = project 1, de...

Colocation (War Room)

Team

Colocation places the team physically together — same room or floor — to maximize the highest-bandwidth commun...

Communication Management Plan

Communication

The communication management plan defines who needs what information, when, in what format, and from whom — pl...

Complexity

Fundamentals

Complexity is the project characteristic arising from many interacting elements — human behavior, system inter...

Component Authorization

Governance

Component authorization is the formal process by which a program manager officially approves a component proje...

Component Projects

Program

Components are the projects, subsidiary programs, and other work inside a program. Each has its own manager, p...

Conflict Resolution Techniques

Leadership

PMI recognizes five approaches: collaborate/problem-solve (dig into the real issue, win-win — the default righ...

Constraint

Fundamentals

A constraint is a limiting factor the project must work within — a fixed deadline, a capped budget, a regulati...

Contingency Plan

Risk

A contingency plan is the pre-built response that executes if an identified risk fires — designed calmly in ad...

Contingency Reserve

Risk

Contingency reserve is time or money set aside for identified risks — the "known unknowns" already sitting in...

Continuous Delivery

Engineering

Continuous delivery keeps the product permanently releasable: every change that passes the automated pipeline...

Continuous Integration (CI)

Engineering

Continuous integration means every developer merges small changes into the shared mainline at least daily, and...

Control Account

Cost

A control account is a management point on the WBS where scope, budget, actual cost, and schedule are integrat...

Control Chart

Quality

A control chart plots process measurements over time against a center line and statistically derived upper/low...

Corrective & Preventive Action

Monitoring

Corrective action realigns performance with the plan after a deviation has occurred; preventive action interve...

Cost Baseline

Cost

The cost baseline is the approved, time-phased budget for the project work — not just a total, but when the mo...

Cost of Quality (CoQ)

Quality

Cost of quality is everything you spend because quality matters — split into the cost of conformance (preventi...

Cost Performance Index (CPI)

EVM & Cost

CPI measures cost efficiency: how much value the project earns for every dollar spent. A CPI of 1.0 means you'...

Cost Variance (CV)

EVM & Cost

Cost Variance is the dollar gap between the value of the work performed and what it cost: negative means over...

Cost-Benefit Analysis

Business

Cost-benefit analysis compares what an option costs against what it returns, in money, so alternatives can be...

Cost-Reimbursable Contract

Procurement

In a cost-reimbursable (cost-plus) contract, the buyer pays the seller's legitimate actual costs plus a fee —...

Crashing

Schedule

Crashing is schedule compression by adding resources to critical path activities — more people, overtime, prem...

Critical Chain Method (CCM)

Schedule

Critical chain scheduling accounts for resource limits, not just task logic, and attacks a human truth: people...

Critical Path

Schedule

The critical path is the longest sequence of dependent activities through a project — and therefore the shorte...

Critical Path Method (CPM)

Schedule

The Critical Path Method is the analytical technique behind the critical path: a forward pass through the netw...

Cross-Functional Team

Agile

A cross-functional team contains, inside itself, every skill needed to turn an idea into a finished increment...

Crystal Methods

Agile

Crystal (Alistair Cockburn) is a family of methods tuned by team size and criticality — Crystal Clear for a co...

Cumulative Flow Diagram (CFD)

Agile

A cumulative flow diagram stacks the count of work items in each state (to do, in progress, done) over time as...

Customer

Stakeholder

The customer is whoever will approve and manage the project's product, service, or result — and often the one...

Cycle Time

Agile

Cycle time measures how long a work item takes from when work starts on it to when it's done. Its sibling, lea...

D

Daily Standup (Daily Scrum)

Agile

The daily standup is a 15-minute team synchronization: inspect progress toward the sprint goal, surface impedi...

Dashboard

Monitoring

A dashboard presents project health at a glance — KPIs, trends, RAG statuses, burn charts — tailored to its au...

Data Date (Status Date)

Schedule

The data date is the as-of point for all project status: everything to its left is actuals, everything to its...

Decision Tree Analysis

Risk

A decision tree maps a choice and its uncertain outcomes as branches, attaches probabilities and payoffs to ea...

Decomposition

Scope

Decomposition is the technique of breaking scope into smaller, more manageable pieces — the engine behind the...

Definition of Done (DoD)

Agile

The Definition of Done is the team's shared, explicit checklist of what "complete" means for every increment —...

Definition of Ready

Agile

The definition of ready is the team's checklist for backlog items entering a sprint: clear enough, small enoug...

Deliverable

Fundamentals

A deliverable is any unique, verifiable product, result, or capability a project must produce — tangible (a bu...

Delphi Technique

Planning

The Delphi technique gathers expert judgment anonymously and in rounds: experts answer independently, a facili...

Dependency Types (FS, SS, FF, SF)

Schedule

Four logical relationships link activities: Finish-to-Start (successor starts after predecessor finishes — 90%...

Design of Experiments (DOE)

Quality

Design of experiments is the statistical method for testing multiple factors simultaneously to find which ones...

Design Thinking

Agile

Design thinking is a human-centered problem-solving cycle: empathize with users, define the real problem, idea...

Development Team (Developers)

Agile

The development team — current Scrum Guide just says "developers" — is everyone who builds the increment: engi...

DevOps

Engineering

DevOps collapses the wall between development ("change fast") and operations ("stay stable") into one culture...

Disbenefit

Program

A disbenefit is a genuinely negative outcome a program creates for some stakeholder as a consequence of succee...

DSDM (Dynamic Systems Development Method)

Agile

DSDM is one of agile's elders (1994), distinctive for wrapping iterative delivery in full project governance:...

Duration vs Effort

Schedule

Effort is the labor content (40 person-hours); duration is the calendar time it occupies (could be 1 day with...

E

Earned Value (EV)

EVM & Cost

Earned Value is the budgeted worth of the work actually completed — not what you spent, but what the finished...

Earned Value Management (EVM)

EVM & Cost

Earned Value Management is the technique that answers the question every sponsor eventually asks: "You've spen...

Emergent Risk

Risk

Emergent risks are the ones that couldn't have been identified in advance — unknowable unknowns arising from c...

Emotional Intelligence (EI)

Leadership

Emotional intelligence is the ability to recognize and manage your own emotions and to read and respond to oth...

Enterprise Environmental Factors (EEFs)

Fundamentals

Enterprise environmental factors are the conditions around your project that you don't control but must plan w...

Enterprise Risk Management (ERM)

Risk

ERM manages risk at the whole-organization level — strategic, financial, operational, reputational, compliance...

Epic

Agile

An epic is a body of work too large to finish in one sprint — a container that gets progressively broken into...

Escalation (Escalation Path)

Governance

Escalation is deliberately moving an issue, risk, or decision to a higher authority because it exceeds your ow...

Estimate at Completion (EAC)

EVM & Cost

Estimate at Completion is the forecast of what the whole project will actually cost, given performance so far....

Estimate to Complete (ETC)

EVM & Cost

Estimate to Complete answers the forward-looking question: "from this point, how much more money do we need to...

Expected Monetary Value (EMV)

Risk

Expected monetary value converts an uncertain event into a single planning number: probability × impact. Threa...

Expert Judgment

Planning

Expert judgment means consulting people with relevant specialized knowledge — team members, consultants, other...

Extreme Programming (XP)

Agile

XP is the agile method with the strongest engineering opinions: pair programming, test-driven development, con...

F

Fallback Plan

Risk

The fallback plan is plan C: what you execute if the risk occurs and the primary response (the contingency pla...

Fast Tracking

Schedule

Fast tracking compresses the schedule by performing activities in parallel that were planned in sequence. It c...

Feasibility Analysis

Business

A feasibility analysis tests whether a proposed project can realistically succeed before serious money commits...

Feature

Agile

A feature is a coherent chunk of product capability that delivers value a user can recognize — bigger than a s...

Feature-Driven Development (FDD)

Agile

FDD is an agile method built around a features list: develop an overall object model, list the features (small...

Fishbone Diagram (Ishikawa)

Quality

The fishbone (Ishikawa, cause-and-effect) diagram puts one problem at the fish's head and organizes potential...

Fixed Formula Method (50/50 Rule)

Cost

The fixed formula method credits earned value in preset chunks: 50/50 (half when the activity starts, half at...

Fixed-Price Contract

Procurement

In a fixed-price (lump sum) contract, the seller commits to deliver defined scope for a set price — and eats a...

Float (Slack)

Schedule

Float (also called slack) is how long an activity can be delayed without pushing the project's finish date. Ac...

Forward Pass & Backward Pass

Schedule

The forward pass walks the network left to right computing each activity's earliest start and finish; the back...

Free Float

Schedule

Free float is the tighter cousin of total float: how long an activity can slip without delaying the early star...

Functional Organization

Organization

In a functional organization, staff are grouped by specialty — engineering, marketing, finance — and report to...

G

H

I

Impact Mapping

Agile

Impact mapping draws a four-level tree from goal to backlog: Why (the measurable goal) → Who (actors who can m...

Impediment (Blocker)

Agile

An impediment is anything slowing or stopping the team's progress: a blocked dependency, a missing decision, a...

Increment

Agile

The increment is the sum of all backlog items completed during a sprint plus all prior increments — a concrete...

Incremental Value Delivery

Value

Incremental value delivery means releasing usable value in slices throughout the project instead of one big ba...

Influence Diagram

Risk

An influence diagram is a compact graph of a decision situation: decisions (squares), uncertainties (circles),...

Information Radiator

Agile

An information radiator is a large, always-visible display of project truth — task board, burndown, build stat...

Integrated Change Control

Integration

Integrated change control is the discipline of reviewing every change request, assessing its impact across all...

Internal Rate of Return (IRR)

Business

IRR is the discount rate at which a project's NPV equals exactly zero — effectively the project's implied annu...

Issue Log

Monitoring

The issue log tracks problems that have already happened and need resolution: each issue gets an owner, a prio...

Iteration

Agile

An iteration is a fixed-length development cycle — plan a slice, build it, review it, improve the process, rep...

Iterative vs Incremental Development

Agile

Incremental delivers finished pieces one at a time — each increment is done, but the product grows part by par...

K

L

M

Make-or-Buy Analysis

Procurement

Make-or-buy analysis is the structured decision between producing something in-house and procuring it: compare...

Management Reserve

Risk

Management reserve is budget or schedule held for the truly unforeseen — the "unknown unknowns" no risk worksh...

Management Reserve (Program)

Finance

A management reserve at the program level is a budget set aside to handle unknown-unknown risks — events that...

Matrix Organization

Organization

A matrix blends functional and projectized structures: people keep a functional home (and boss) while also ans...

Methodology

Fundamentals

A methodology is a defined system of practices, techniques, procedures, and rules for running projects — PRINC...

Milestone

Schedule

A milestone is a significant point or event in the project — a phase gate passed, a major deliverable accepted...

Mind Mapping

Planning

Mind mapping radiates ideas from a central concept outward into branches and sub-branches, capturing structure...

Minimum Viable Product (MVP)

Agile

An MVP is the smallest version of a product that delivers real value to real users while maximizing what the t...

Mob Programming

Engineering

Mob programming is the whole team working on one problem at one screen: a single driver types (rotating every...

Monte Carlo Simulation

Risk

Monte Carlo simulation is a quantitative risk technique that runs a project model thousands of times with rand...

MoSCoW Prioritization

Agile

MoSCoW sorts requirements into four buckets: Must have (without these, the release fails or is illegal), Shoul...

Motivation Theories (Maslow, Herzberg, McGregor)

Leadership

The exam's big three: Maslow's hierarchy — needs stack from physiological through safety, social, and esteem t...

Multicriteria Decision Analysis (Weighted Scoring)

Planning

Multicriteria decision analysis evaluates options against several weighted criteria in a matrix: define criter...

N

O

OKRs (Objectives and Key Results)

Business

OKRs pair a qualitative, inspiring Objective ("make onboarding effortless") with 3–5 measurable Key Results th...

Operational Readiness

Program

Operational readiness is the verified state where the receiving organization can actually run what's being del...

Opportunity (Positive Risk)

Risk

An opportunity is a risk with an upside — an uncertain event that would help objectives if it occurred. It get...

Organizational Breakdown Structure (OBS)

Resource

The OBS is the hierarchical chart of the project organization — departments, teams, units — arranged so work c...

Organizational Change Management (OCM)

Integration

OCM prepares people to adopt what projects deliver: stakeholder readiness, communication, training, champions,...

Organizational Change Management (Program)

Strategy

Organizational change management at the program level is the discipline of preparing, supporting, and guiding...

Organizational Process Assets (OPAs)

Fundamentals

Organizational process assets are everything your organization has learned and standardized that you can reuse...

Osmotic Communication

Agile

Osmotic communication (Alistair Cockburn, Crystal) is the useful information team members absorb from backgrou...

Output vs Outcome

Fundamentals

An output is what the project produces — the system, the building, the report. An outcome is the changed condi...

Overall Project Risk

Risk

Overall project risk is the uncertainty of the project as a whole — the combined effect of all individual risk...

P

Pacing (Program)

Program

Pacing is deliberately timing component starts, finishes, and outputs so the program flows: benefits arrive wh...

Pair Programming

Engineering

Pair programming puts two developers on one problem at one screen: the driver types, the navigator reviews con...

Parametric Estimating

Cost

Parametric estimating multiplies a unit rate by a quantity: cost per square meter × square meters, hours per t...

Pareto Chart

Quality

A Pareto chart is a bar chart of problem causes sorted from most to least frequent, usually with a cumulative-...

Path Convergence & Divergence

Schedule

Path convergence is multiple network paths merging into one activity — that node needs all of them finished, s...

Payback Period

Business

The payback period is how long an investment takes to earn back its initial cost — the simplest project-select...

Performance Measurement Baseline (PMB)

Cost

The PMB is the integrated scope-schedule-cost baseline that earned value measures against: the WBS says what,...

Performing Organization

Organization

The performing organization is the enterprise whose people actually do the project work — the contractor build...

Persona

Agile

A persona is a fictional but research-grounded archetype of a user — name, role, goals, frustrations, context...

PESTLE Analysis

Planning

PESTLE scans the macro environment across six lenses: Political, Economic, Social, Technological, Legal, Envir...

Phase Gate (Stage Gate)

Governance

A phase gate is a formal checkpoint at a phase's end where governance reviews performance and the business cas...

Phase-Gate Review

Governance

A phase-gate review is a formal decision point in a program's life cycle where the program's governance board...

Plan-Do-Check-Act (PDCA)

Quality

PDCA — the Shewhart/Deming cycle — is the engine of continuous improvement: Plan a change with a predicted out...

Planned Value (PV)

EVM & Cost

Planned Value is the authorized budget for the work scheduled to be done by a given date — in plain terms, "wh...

Planning Poker

Agile

Planning poker is consensus-based estimation: each team member privately picks a card (usually Fibonacci — 1,...

PMBOK Guide

Fundamentals

The PMBOK® Guide is PMI's foundational standard for project management. The 7th edition (2021) reframed it aro...

PMP Exam 2026: What's New

Exam

The 2026-era PMP continues three domains — People, Process, Business Environment — with roughly half of questi...

Portfolio Balancing

Organization

Portfolio balancing is the ongoing act of tuning the investment mix — risk versus return, short-term versus st...

Portfolio Management

Organization

Portfolio management selects and balances the organization's whole collection of projects and programs against...

Power/Interest Grid

General

The power/interest grid classifies stakeholders along two axes — their power over the project and their intere...

Precedence Diagram Method (Network Diagram)

Schedule

The precedence diagram method (PDM) draws the schedule as a network: activities are boxes, dependencies are ar...

Precision vs Accuracy

Quality

Accuracy means close to the true value; precision means measurements cluster tightly together. They're indepen...

Predictive Life Cycle (Waterfall)

Fundamentals

A predictive (plan-driven, waterfall) life cycle fixes scope, schedule, and cost early, then executes phase by...

Probability and Impact Matrix

Risk

The probability-impact (P×I) matrix is the grid that turns qualitative risk scores into priorities: probabilit...

Process Groups (IPECC)

Fundamentals

The five process groups — Initiating, Planning, Executing, Monitoring & Controlling, Closing (IPECC) — organiz...

Procurement Audit

Procurement

A procurement audit is the structured review of the procurement process itself — from planning through contrac...

Procurement Documents (RFP, RFQ, IFB)

Procurement

The three bid documents map to what the buyer knows: RFQ (request for quotation) — commodity purchase, price i...

Procurement Management Plan

Procurement

The procurement management plan defines how the project will buy: what gets procured versus made, contract typ...

Product Backlog

Agile

The product backlog is the single, ordered list of everything that might be built — features, fixes, improveme...

Product Life Cycle

Fundamentals

The product life cycle spans a product's whole existence — introduction, growth, maturity, decline, retirement...

Product Owner

Agile

The product owner owns the what and the why: maximizing product value by managing and ordering the product bac...

Product Roadmap

Agile

A product roadmap communicates direction over time: themes and outcomes now / next / later — deliberately coar...

Product Scope vs Project Scope

Scope

Product scope is the features and functions of the thing being delivered; project scope is all the work requir...

Program Audits & Compliance

Governance

Program audits are independent examinations of whether the program follows its governance, manages money and r...

Program Change Management

Program

At program level, change management means two linked things: controlling changes to program scope, roadmap, an...

Program Charter

Program

The program charter authorizes the program: its vision, intended benefits, scope at program level, key compone...

Program Closure

Program

Program closure is the final phase: confirm remaining benefits are transitioned to sustainment owners, close o...

Program Collaboration

Team

Collaboration in program management means creating the conditions where component teams, the program core team...

Program Contingency Reserve

Finance

A program contingency reserve is budget set aside at the program level to cover the financial impact of identi...

Program Core Team

Team

The program core team is the group of senior professionals who work directly with the program manager to plan,...

Program Definition Phase (Formulation & Planning)

Program

Program definition is the first life-cycle phase, in two movements: formulation — shape the business case, sec...

Program Financial Framework

Program

The program financial framework defines how money flows through the program: funding sources and their timing,...

Program Formulation

Life Cycle

Program formulation is the first sub-phase within the program definition phase, where the program's basic stru...

Program Governance

Program

Program governance is the framework of oversight: the governance board, phase-gate reviews, escalation thresho...

Program Infrastructure Development

Integration

Program infrastructure development is the process of establishing the foundational structures, tools, processe...

Program Integration Management

Program

Program integration management coordinates everything that crosses component boundaries: interdependencies, sh...

Program Life Cycle

Program

PMI's program life cycle has three phases: definition (build the business case, charter, and roadmap), deliver...

Program Management

Program

Program management coordinates a group of related projects (and other work) as one entity to capture benefits...

Program Manager vs Project Manager

Program

The project manager delivers defined scope on time and budget; the program manager delivers benefits through m...

Program Master Schedule

Schedule

The program master schedule is the high-level schedule that shows how all of a program's component projects an...

Program Performance Baseline

Performance

The program performance baseline is the approved, integrated reference point for measuring program performance...

Program Procurement Management

Procurement

Program procurement management covers how a program plans, executes, and controls the acquisition of goods and...

Program Resource Management Plan

Resources

The program resource management plan defines how resources — people, equipment, budget, and materials — will b...

Program Risk Thresholds

Program

Program risk thresholds are the quantified limits that define which risks belong at which level: below the lin...

Program Roadmap

Program

The program roadmap is the chronological big picture: components, major milestones, key dependencies, and — cr...

Program Sponsor

Governance

The program sponsor is the senior executive or organizational leader who champions the program at the highest...

Program Stakeholder Engagement

Program

Program stakeholder engagement manages a landscape wider and more political than any project's: executives, re...

Program Vision

Program

The program vision is the concise picture of the future state the program exists to create — vivid enough to a...

Program Work Breakdown Structure (PWBS)

Program

The program WBS decomposes the program to the level where components take over: program-level deliverables, th...

Progressive Elaboration

Fundamentals

Progressive elaboration is the principle that project plans get continuously more detailed and accurate as bet...

Project Calendar

Schedule

The project calendar defines when project work may happen — working days, shifts, holidays, seasonal windows —...

Project Charter

Integration

The project charter is the document that formally authorizes a project to exist and names the project manager....

Project Governance

Governance

Project governance is the oversight framework around a project: who approves what, how decisions above the PM'...

Project Life Cycle

Fundamentals

The project life cycle is the series of phases a project passes through from start to close — commonly startin...

Project Management Information System (PMIS)

Integration

The PMIS is the integrated tool environment the project runs on: scheduling software, cost tracking, document...

Project Management Office (PMO)

Organization

A PMO standardizes project governance and supports project managers. PMI's three types by control level: suppo...

Project Management Plan

Integration

The project management plan is the master playbook: how the project will be executed, monitored, and closed. I...

Project Phase

Fundamentals

A project phase is a collection of logically related activities culminating in the completion of one or more d...

Project Scope Statement

Scope

The scope statement describes, in writing, what the project will deliver and — just as important — what it won...

Project Sponsor

Stakeholder

The sponsor is the person (or group) who provides the money and the political air cover, champions the project...

Project Success Criteria

Fundamentals

Project success is multi-layered and must be defined before delivery starts: project management success (scope...

Projectized Organization

Organization

In a projectized organization, the project is the primary structure: teams are dedicated, colocated around the...

Projects vs Operations

Fundamentals

A project is temporary and unique: it has a start, an end, and produces something that didn't exist. Operation...

Prompt List (PESTLE, TECOP, VUCA)

Risk

A prompt list is a predetermined set of risk categories used to systematically jog identification — walk each...

Psychological Safety

Team

Psychological safety is the shared belief that the team is safe for interpersonal risk — you can ask the naive...

Q

R

RACI Chart

General

A RACI chart maps every activity to who is Responsible (does the work), Accountable (owns the outcome — exactl...

Refactoring

Engineering

Refactoring improves code's internal structure without changing its external behavior — renaming for clarity,...

Release Planning

Agile

Release planning maps backlog to time at the medium range: which features land in which release, driven by eit...

Requirements Elicitation

Business

Elicitation is actively drawing requirements out of stakeholders and sources — interviews, workshops, observat...

Requirements Traceability Matrix (RTM)

Scope

The requirements traceability matrix is a table linking every requirement to its origin (business need, stakeh...

Reserve Analysis

Cost

Reserve analysis sizes and then monitors the project's buffers: contingency reserve for identified risks (insi...

Residual Risk

Risk

Residual risk is what's left after a risk response is implemented. Mitigation reduces a risk; it rarely erases...

Resource Breakdown Structure (RBS)

Resource

The resource breakdown structure is a hierarchical view of resources by category and type — labor (by trade an...

Resource Calendar

Resource

A resource calendar shows when each specific resource — a person, a crane, a test lab — is actually available...

Resource Histogram

Resource

A resource histogram is a bar chart of resource demand over time — hours or headcount per week, stacked by rol...

Resource Leveling

Resource

Resource leveling adjusts the schedule to resolve overallocation — when the plan needs a person or machine in...

Resource Smoothing

Resource

Resource smoothing evens out resource demand by shifting activities only within their available float — peaks...

Responsibility Assignment Matrix (RAM)

Resource

A responsibility assignment matrix maps work (rows) to people or roles (columns) so every piece of work has ex...

Retrospective

Agile

The retrospective is the recurring meeting — end of every sprint — where the team inspects its own process: wh...

Return on Investment (ROI)

Business

ROI expresses net benefit as a percentage of cost: what did each invested dollar give back? It's the most wide...

Rework

Quality

Rework is doing work again because it wasn't right the first time — the purest form of internal failure cost a...

Risk Appetite

Risk

Risk appetite is how much uncertainty an organization is willing to accept in pursuit of its objectives — a st...

Risk Appetite, Tolerance & Threshold

Risk

Three nested dials: appetite is the general disposition — how much uncertainty the organization is willing to...

Risk Audit & Risk Reassessment

Risk

Two distinct check-ups: a risk reassessment re-examines the risks themselves — new ones identified, stale ones...

Risk Breakdown Structure (RBS)

Risk

The risk breakdown structure is a hierarchical chart of risk categories — technical, external, organizational,...

Risk Burndown Chart

Risk

A risk burndown chart plots total risk exposure (sum of probability × impact across the register) over time —...

Risk Categories

Risk

Risk categories group risks by source — technical, external, organizational, project-management (the classic R...

Risk Data Quality Assessment

Risk

Risk data quality assessment checks how trustworthy the information behind each risk rating is — accuracy, rel...

Risk Exposure

Risk

Risk exposure is the quantified amount of risk carried — for one risk, probability × impact (its EMV); for a p...

Risk Management Plan

Risk

The risk management plan defines how risk will be managed on this project — methodology, roles, categories (th...

Risk Owner

Risk

The risk owner is the single named person accountable for monitoring a specific risk and executing its respons...

Risk Register

Risk

The risk register is the living log of identified risks: each entry with its description, probability, impact,...

Risk Response Strategies

Risk

For threats there are five responses: avoid (eliminate the risk by changing the plan), mitigate (reduce probab...

Risk Threshold

Risk

A risk threshold is the measurable line drawn from risk appetite — the specific level of exposure above which...

Risk Trigger (Trigger Condition)

Risk

A risk trigger is the observable warning sign that a risk is about to occur or has begun — the tripwire that a...

Rolling Wave Planning

Planning

Rolling wave planning means planning near-term work in detail and leaving far-future work at a higher level, e...

S

S-Curve

Cost

The S-curve is cumulative cost (or work) plotted over time. It's S-shaped because projects spend slowly at fir...

SAFe (Scaled Agile Framework)

Scaling

SAFe is the most widely adopted framework for running agile across many teams: Agile Release Trains (5–12 team...

Salience Model

Stakeholder

The salience model classifies stakeholders on three attributes: power (can they impose their will?), legitimac...

Scatter Diagram

Quality

A scatter diagram plots two variables against each other, one dot per observation, to reveal whether they move...

Schedule Baseline

Schedule

The schedule baseline is the approved version of the schedule — the fixed reference that actual progress is me...

Schedule Performance Index (SPI)

EVM & Cost

SPI measures schedule efficiency: the rate at which work is actually being completed versus the rate the plan...

Schedule Variance (SV)

EVM & Cost

Schedule Variance expresses schedule position in dollars: the value of work completed minus the value of work...

Scope Baseline

Scope

The scope baseline is the approved definition of what the project will deliver: the scope statement, the WBS,...

Scope Creep

Scope

Scope creep is the uncontrolled growth of project scope — additions that bypass change control, arriving one "...

Scrum

Agile

Scrum is the most widely used agile framework: small cross-functional teams deliver working product in fixed-l...

Scrum Master

Agile

The scrum master is the team's servant-leader and process guardian: coaching Scrum practice, removing impedime...

Scrum of Scrums

Scaling

Scrum of scrums scales coordination: each team sends a representative to a regular cross-team standup focused...

Secondary Risk

Risk

A secondary risk is a brand-new risk created by your risk response itself. You fixed one problem and your fix...

Self-Organizing Team

Agile

A self-organizing team decides internally how to accomplish its work — who takes what, how to solve problems,...

Sensitivity Analysis (Tornado Diagram)

Risk

Sensitivity analysis asks: which input uncertainties move the outcome most? Vary one factor at a time across i...

Servant Leadership

Leadership

Servant leadership inverts the traditional pyramid: the leader's job is to serve the team — removing impedimen...

Siloed Organization

Organization

A siloed organization groups people by specialty — analysis, development, testing, operations — so value must...

Smoke Testing

Engineering

A smoke test is the fast sanity check that a build's vital functions work at all — can it start, log in, load...

Source Selection Criteria

Procurement

Source selection criteria are the published, weighted factors used to score seller proposals: technical approa...

Spike

Agile

A spike is a timeboxed investigation whose deliverable is knowledge, not product: research a technology, proto...

Sprint

Agile

A sprint (or iteration) is a short, fixed-length timebox — commonly two weeks — in which the team plans, build...

Sprint Backlog

Agile

The sprint backlog is the developers' plan for the sprint: the sprint goal, the product backlog items selected...

Sprint Planning

Agile

Sprint planning opens each sprint: the team answers why (craft a sprint goal), what (select backlog items the...

Sprint Review

Agile

The sprint review closes the sprint's product loop: the team demonstrates the working increment to stakeholder...

Stakeholder

Stakeholder

A stakeholder is any individual, group, or organization that can affect, be affected by, or merely perceive it...

Stakeholder Analysis

Stakeholder

Stakeholder analysis systematically works out who your stakeholders are, what they want, how much they matter,...

Stakeholder Engagement Assessment Matrix

Stakeholder

This matrix compares each stakeholder's current engagement level against the level you need: unaware, resistan...

Stakeholder Engagement Plan

Stakeholder

The stakeholder engagement plan turns analysis into strategy: for each key stakeholder or group, the desired e...

Stakeholder Register

General

The stakeholder register is the catalog of everyone who can affect or be affected by the project — with their...

Statement of Work (SOW)

Procurement

The statement of work is the narrative description of the products, services, or results to be delivered — in...

Steering Committee (Governance Board)

Program

The steering committee (program governance board) is the senior group that owns the big decisions: approving t...

Story Points

Agile

Story points are a relative, unitless measure of effort — this item is roughly twice that one — covering compl...

Strategic Alignment

Program

Strategic alignment is the continuous fit between a program and the organization's strategy — checked at initi...

Subprogram

Fundamentals

A subprogram is a group of related projects and activities within a larger program that are managed together b...

Subsidiary Management Plans

Integration

The project management plan is a binder of subsidiary plans, one per discipline: scope, requirements, schedule...

Summary Activity (Hammock)

Schedule

A summary (hammock) activity is a single bar representing a group of related activities — its dates and durati...

Sunk Cost

Business

A sunk cost is money already spent and unrecoverable — and therefore, rationally, irrelevant to any decision a...

Sustainability in Project Management (ESG)

Emerging

Sustainability in projects means managing environmental, social, and governance impact as first-class constrai...

Swarming

Agile

Swarming is the whole team (or most of it) converging on one work item to finish it before starting anything e...

SWOT Analysis

Risk

SWOT examines a project or decision from four angles: internal Strengths and Weaknesses, external Opportunitie...

Synergy (Program)

Program

Synergy is the extra value created when components are managed together — benefits unavailable to the same pro...

T

Tailoring

Fundamentals

Tailoring is deliberately selecting which processes, methods, and artifacts fit this project — instead of runn...

Team Charter & Ground Rules

Team

The team charter is the team's social contract, written by the team itself: values, working agreements, commun...

Team of Teams

Team

Team of teams is a program management principle introduced in the 5th edition of the PMI Standard for Program...

Technical Debt

Engineering

Technical debt is the accumulated future cost of past shortcuts — quick hacks, skipped tests, outdated depende...

Test Plan

Quality

A test plan defines how deliverables will be verified: what gets tested at which levels (unit, integration, sy...

Test-Driven Development (TDD)

Engineering

TDD inverts the usual order: write a failing test first (red), write the minimum code to pass it (green), then...

Three-Point Estimating (PERT)

Cost

Three-point estimating replaces a single guess with three: optimistic (O), most likely (M), and pessimistic (P...

Throughput

Agile

Throughput is the count of work items finished per time period — ten stories a week, forty tickets a month. Wi...

Time and Materials (T&M) Contract

Procurement

A time and materials contract pays for hours worked at agreed rates plus materials at cost — a hybrid sitting...

Timeboxing

Agile

Timeboxing fixes the time and lets the content flex: the meeting is 15 minutes, the sprint is 2 weeks, the spi...

To-Complete Performance Index (TCPI)

EVM & Cost

TCPI is the efficiency the project must achieve on all remaining work to finish within a target budget — essen...

Total Cost of Ownership (TCO)

Business

Total cost of ownership is the full life-cycle price of an option: acquisition plus operation, maintenance, tr...

Trend & Regression Analysis

Monitoring

Trend analysis reads performance over time — CPI drifting down for three periods says more than any single val...

Triple Constraint (Iron Triangle)

Fundamentals

The triple constraint — scope, time, cost, with quality living in the middle — says the three sides are linked...

Tuckman Ladder (Team Development Stages)

Team

Tuckman's model says teams develop through five stages: forming (polite, uncertain, leader-dependent), stormin...

U

V

Validate Scope

Scope

Validate Scope is the customer formally accepting completed deliverables. Its exam twin, Control Quality, is t...

Value Delivery

Value

Value delivery is the through-line of the modern PMP exam: projects exist to deliver value — to customers, the...

Value Delivery System (PMBOK 7)

Value

The value delivery system is PMBOK 7's big frame: portfolios, programs, projects, products, and operations wor...

Value Proposition

Business

A value proposition states why someone should choose this — the specific benefit, for a specific audience, ver...

Value Realization

Value

Value realization is value actually arriving — measured, in the books, in the mission — as opposed to value pr...

Value Stream Mapping

Lean

Value stream mapping draws every step from request to delivered value, timing each one and — crucially — the w...

Value-Based Prioritization

Value

Value-based prioritization orders work by value contribution — economic (revenue, savings, cost of delay), ris...

Variance Analysis

Monitoring

Variance analysis compares actual performance to baseline, quantifies the gap (cost variance, schedule varianc...

Variance at Completion (VAC)

EVM & Cost

Variance at Completion is the projected difference between the original budget and the forecast final cost — t...

Velocity

Agile

Velocity is the amount of work (usually story points) a team actually completes per sprint, averaged over rece...

Verification vs Validation

Quality

Verification asks: did we build the thing right — does it conform to specifications and requirements? (Interna...

Virtual Teams

Team

Virtual teams work toward shared goals with little or no face time — distributed across cities, countries, and...

W